In the shadow of two outdated smokestacks and four
antiquated coal-fired boilers, Ball State has started the second and final
phase of converting the university to a geothermal ground-source heat pump
system - the largest project of its kind in the United States.
The conversion, started in 2009 to
replace the coal boilers, now provides heating and cooling to nearly half the
campus. This phase of the project will be dedicated in March.
When the system is complete, the shift
from fossil fuels to a renewable energy source will reduce the university's
carbon footprint by nearly half while saving $2 million a year in operating
costs.
Ball State is installing a vertical,
closed-loop district system that uses only fresh water. The system uses the
Earth's ability to store heat in the ground and water thermal masses. A
geothermal heat pump uses the Earth as either a heat source, when operating in
heating mode, or a heat sink, when operating in cooling mode.
Under the direction of Jim Lowe,
director of engineering, construction and operations, work has begun on Phase
2, which includes installation of 780 of the remaining 1,800 boreholes in a
field on the south area of campus.
Construction will continue throughout
2013-2014 and will include a new District Energy Station South containing two
2,500-ton heat pump chillers and a hot water loop around the south portion of
campus.
The system will then connect to all
buildings on campus - eventually providing heating and cooling to 5.5 million ft2.
"When costs began to escalate for
the installation of a new fossil fuel burning boiler, the university began to
evaluate other renewable energy options," Lowe says. "This led to the
decision to convert the campus to a more efficient geothermal-based heating and
cooling system."
The project has caught the attention of
universities and communities across the nation. Lowe is sharing information
about the university's new operation with others who want learn how they too can
benefit from a geothermal system.